Friday, February 11, 2011

Town Green Construction Progress, 2/11/11

Click to Enlarge
Weather caused several disruptions in the work schedule this week, but a great forecast is ahead of us for next week.

Next week the contractor will begin the final phases of site prep and driveway work on the western half of the project area.  This has major implications to businesses facing Broad Street because all access to parking and deliveries in the east back lot will be closed for the remainder of the project. 

This week work continued on the blue stone walkways and brick paved interior circle.  Dumpster pads continued to be completed, and the northern driveway was poured and saw cut. 

As we move into the final stages of the project there are seven major tasks to be completed:

  1. Concrete pours of the western driveway.
  2. Completion of detailed masonry work.
  3. Completion of dumpster pads.
  4. Demolition and construction of the alleyway leading to Broad Street.
  5. Installation of ancillary vegetation, trees and sod. 
  6. Completion of the irrigation system.
  7. Finishing of the parking areas.

The contractor deadline is March 24th, which is roughly five weeks away.  If the weather continues to cooperate, we may be able to beat this deadline.




A crew member works in the alley connecting Broad Street to the Town Green


Crew members work on laying brick pavers around the inner ring of the Town Green - Click to Enlarge