Friday, February 18, 2011

Town Green Construction Progress, 2/18/11

The Blue Stone walkway on the Green's perimeter is about 50% complete
Work proceeded quickly this week on the western driveway of the Town Green, as weather conditions were perfect for pouring and setting concrete.  The final section is expected to be poured on Monday.

A mason works on the inner brick walkway

In addition to the driveways, work was completed on three of the four dumpster pads, with the fourth to be completed next week.  Crews will be in town next week to build the walls surrounding the dumpster enclosures.

Brick masons were here laying the pavers into place for the landing areas on all four corners of the Green.  The sitting wall is also fully enclosed at this point.  The contractor is expecting the wall caps to arrive next week.

The dumpster pads have been poured, and the walls will be completed in the coming weeks

Work on the irrigation system will continue through next week, with the system expected to be fully functional by week’s end. 

Work along the alleyway to Broad Street is nearly complete, as the concrete walkway sections were poured this week.  Brick pavers will be put into place between sections in the upcoming week.  Brick columns featuring sconces will also begin being constructed over the weekend.

The alley connecting Broad Street to the Town Green has been rehabilitated

The end is definitely in sight, and the City appreciates everyone’s cooperation through the construction period despite disruptions to parking, deliveries, and trash service.