Monday, March 21, 2011

Town Green Construction Progress, 3/21/2011



Painters work on the inside of one of the dumpster enclosures
 
The finising touches are being put on the Camden Town Green, as construction should conclude in the next few weeks. Workers are installing the wooden siding on the Green's dumpster/transformer enclosures, and crews are painting the inside and outside of the enclosures.

 
A construction crew member sands one of the bollards to prepare it for paint
 
All of the Town Green's bollards - temporary columns meant to control automotive traffic - are being cleaned and painted. They will normally be removed, but installed during events to prohibit cars from entering the area.

The outside of a dumpster enclosure after the first coat of paint has been applied
 The next big visual change will be the smaller trees and foliage, set to arrive soon. The sod is 80% complete, and the remaining 20% will be laid this week. Things are shaping up, and the Town Green is becoming greener by the day.

No comments: