Town Green Construction Progress, 3/11/11

The columns near the alley leading to Broad Street have been wired for lighting
Recently, there was a partial disruption in progress due to a reconfiguration of the irrigation system and reduction in the number and size of plant materials throughout the Town Green.  These changes came at the request of Urban Forester, Liz Gilland.

Despite that, nearly four times the amount of workers are on the job site than at any other time during the project.  Because of the increased manpower, crews were able to complete the Philadelphia Blue Stone sidewalks, the brick columns, brick pavers, and electrical wiring along the alleyway to Broad Street.

the caps for the Green's sitting walls wait to be installed
Yesterday, more good news came as the caps for the sitting walls were delivered and the frames for the dumpster enclosures were treated with the final coats of paint.  Look for work completing the wall caps and dumpster enclosures to run through mid-week next week.

Other details that were addressed over the course of this week include the installation of French drains in the parking areas, installation of concrete surfaces behind Rutledge Gallery, and the construction of parking areas to the north of Camden Insurance Agency.  The remaining light poles for the project will also be installed beginning today through Monday.
A crew works on the last of the concrete to pour